The oil pumping station "Pervomaiskaya". Completion of construction.

    The company "Neftechemservis" six months ahead the schedule completes works on increasing the capacity of the oil pumping station "Pervomaiskaya" of the oil-trunk pipeline "Aleksandrovskoye - Anzhero-Sudzhensk" of the company "AK "Transneft" and ensures guaranteed supplies of raw materials to the Yaya oil refinery in the required volume of 3 million tons per year.

    When meeting the technical conditions of the contract with "AK "Transneft", JSC "Neftechemservis" invested into construction of the facility approximately five billion rubles. At present, all construction and installation works at the site of the oil pumping station "Pervomaiskaya" are completed.

    According to the Customer representative, the Deputy General Director on Construction of JSC "Transneft-Central Siberia" Pavel Burlikov, JSC "Neftechemservis" fulfilled its obligations under the contract; financing for the construction phase was being carried out ahead the schedule, which largely determined the result. The station Pervomaiskaya is ready for commissioning six months ahead the schedule. As per the schedule, start-up of the pumping station was scheduled for July 2015, however already in January comprehensive equipment testing will begin at the station, and in February it will be running at operating mode.

    Considering fulfillment of contractual obligations on the part of JSC "Neftechemservis", the company "AK "Transneft "since May ships the raw materials to the Yaya oil refinery in amounts necessary to fully load the enterprise, i.e. 250 thousand tons per month, which allows to the Kuzbass enterprises operating at full capacity, i.e. 3 million tons per year.


Возврат к списку