Events

 
10.03.2015

Second stage

The Board of Directors of the company "NefteChemServis" approved the strategy of development of the construction project of Yaya oil refinery till 2023.

 According to the approved program the second stage of construction of the plant will consist of five phases:

Terms

Planned works

Investment

Commodity product

1.

2015-2018

Design and construction of the vacuum unit

5 billion rubles

- Straight-run gasoline

 - Diesel fuel

 - Vacuum gas oil

 - Fuel oil M-100

2.

2015-2018

Design and construction of the catalytic reforming and isomerization unit

25 billion rubles

-Petrol 92-95 (Euro-type)

 - Diesel fuel

 - Vacuum gas oil

 - Fuel oil M-100

3.

2015-2020

 

Design and construction of the delayed coking unit

18 billion rubles

-Petrol 92-95 (Euro-type)

 - Diesel fuel

 - Vacuum gas oil

 - Petroleum coke

 - Sulphur

4.

2018-2020

Design and construction of the primary oil processing unit with capacity of 3 million tons

10 billion rubles

- Gasoline 92-95 (Euro-type)

 - Diesel fuel

 - Vacuum gas oil

 - Petroleum coke

 - Sulphur

 - Straight-run gasoline

5.

2020-2023

Design and construction of the Diesel fuel hydrotreatment unit

14 billion rubles

- Petrol 92-95 (Euro-type)
- Diesel fuel (Euro-type)
- Vacuum gas oil
- Petroleum coke
- Sulphur
- Straight-run gasoline