The second stage

The Board of Directors of the company "NefteChemServis has taken a decision to start construction of the first and the second phases of the second stage of the Yaya oil refinery within the approved project development concept until 2023.

At the first phase (2016-2018), in addition to the runningcrude unit (within the reconstruction) there will be implemented a fuel oil vacuum distillation unit with an estimated capacity of 1,600 tons\year that will allow to produce:

- Natural stable gas (STO 11605031 - 019-2007)

- Diesel fuel (STO 74291823.005-2013 with deviations)

- Vacuum gas oil

- Fuel oil. Heavy fuel oil (GOST 10585-2013)

 

Implementation of the fuel oil vacuum distillation unit will allow increasing the rate of depth of oil refining up to 76%.

At the second phase (2016 - 2019) it is planned to implement a combined unit UK-1 for processing straight-run gasoline fractions that will allow producing gasoline of the grade 5 TR TS 013 \ 2013 GOST 51105-97

 The characteristics of the products made at this stage will fully correspond to the quality indicators defined by the standards and technical requirements.

 Currently,a positive decision has beenreceived from the Main Department of the State Expertise for the design documentation for reconstruction of the crude unit.

 Till 30.04.2016 year it is expected to obtain permissionfor construction of the first phase of the second stage of YANPZ. In the nearest future the company "NefteChemServis" is planning to start selection of a general contractor to perform construction and assembly works and to start active work on procurement of basic process equipment for the crude unit of a long cycle. Construction start is scheduled for May 2016.

Investments in construction of the second stage of YANPZ at the first two phases will amount to 30 billion rubles.