To date, 7,240 (97%) tons of metal structures have been assembled out of the required 7,430 tons; 66 thousand (86%) of welded joints of technological pipelines out of 76 thousand. Works have been started on laying of cables and wires. Active work is in progress on installation of electrical equipment in the transformer substations of 10 kW. At the same time, works on arrangement of fire protection systems and anticorrosion protection of the assembled metal structures are being carried out.