The company's development program was developed in accordance with the "Agreement on the creation of new production facilities for deep processing of crude oil" signed by the company's management with the Ministry of Energy of the Russian Federation in August last year.
The project of the third stage of the enterprise involves the construction of two complexes by the end of 2026:
- dewaxing complex with a capacity of 2,600 thousand tons per year;
- delayed coking plants with a capacity of 1,340 thousand tons per year.
LLC "Unix", with which the company has concluded a general contract with expanded functions to perform a full cycle of work on the construction of the third stage of the YaYa refinery, fulfills its obligations in full in strict accordance with the approved schedule. At the moment, active work is underway to develop a basic project.
The licensor of technologies was approved at the next meeting of the company's Board of Directors. The decision in this direction was made taking into account the current economic realities and possible risks. Preference is given to domestic developers. The function of a single technology contractor is defined for LLC "Lengiproneftekhim".
Work on the construction of the third stage is being carried out taking into account two new production sites opened on the basis of “ANGK” LLC and “Severny Kuzbass Refinery” LLC. Due to the new workshops, the capacity of the YaYa Refinery has increased by 1.2 million tons and currently stands at 4.5 million tons per year.
The commissioning of two new complexes will contribute to an increase in the depth of oil refining to 93%, will increase the yield of light petroleum products and establish the production of commercial diesel fuel with improved low-temperature properties.
According to preliminary estimates, the volume of investments in the construction of the third stage of the YaYa refinery will amount to 80 billion rubles. With the launch of two new complexes, the enterprise will open more than 500 new jobs.