The stage of manufacture of the vacuum column K-5 for the Yaya oil refinery is completed. The specialists of the company "NefteChemServis", the representatives of the contracting organization, engaged in installation of equipment(LLC "OMUS-1" Omsk) and the company providing engineering services in the field of industrial safety and non-destructive testing of welded joints (LLC "Technology", Tomsk) carried out acceptance and testing of the column directly at the site of the manufacturer – JSC HC "SDS-Mash".
The Committee came to the conclusion that the equipment fully complies with all stated specifications. In the nearest future the manufacturer will start works on transportation of the unit to the construction site of the Yaya oil refinery.
The column weighing 64 tons, with length of 28 m and diameter of 5 m is to be moved from the city of Kemerovo to the city of Anzhero-Sudzhensk and forth to the Yaya oil refinery. It is more than 100 km.
In October 2017, the company "NefteChemServis" is planning to start commissioning, and in November – to put into operation the column K-5 capable of processing up to 1560 thousand tons of fuel oil a year. This will allow to the Yaya oil refinery to increase the output of light petroleum products ( diesel fractions and vacuum gasoil) and to bring the depth of oil refining up to 75%.