Company "NefteKhimServis" in the Siberian Department of Federal Service for Ecological, Technological and Nuclear Supervision sent a notification about the beginning of construction works.
Within the scope of the construction program of Stage 2 (Phase 1) of Yaya Refinery - reconstruction of the CDU-AVT, General Contractor - JSC "Omus-1" - began production of temporary facilities - construction of the headquarters building and the construction of the site barrier. In the near future it is scheduled to begin pad works for materials warehousing, works on power supply equipment, excavations and pile foundation jobs. All activities are conducted in full accordance with the approved schedule. In early July, construction materials for the zero cycle jobs production will start to arrive to the Yaya Refinery site.