The Yaya Oil Refinery Plant approached the regular operating schedule after the preventive heavy repair.
Within 15 days specialists of the plant together with the representatives of contractors carried out re-piping of stripping column, cleaned technological devices and made diagnostics of pipelines, vessels and equipment working under pressure. Hydraulic pressure testing of equipment was started on 16 June and on 18 June, the company has reached a normal operating mode with the shipment of marketable products.
The scheduled preventive repair was carried out in order to prevent emergencies and ensure smooth and trouble-free operation of the Yaya Refinery main technological equipment.